
Norochcholai
to herald new power era
To add 900 MW to
National Grid by 2011
By Santhush Fernando
With Sri Lanka’s exponential growth and anticipated GDP growth
comes the exponential need for energy. Demand for electricity
has far outstripped supply, and now a new era will dawn in Sri
Lanka’s power and energy sector with the Norochcholai Coal Power
Project coming into operation by mid 2010 heralding the Coal
Power Era.
The Nation team visited Norochcholai Power Plant last week,
and was able to see that nearly 70 percent of its civil
construction was over and the project is ahead of its schedule
in completing work.
Speaking at a press conference held at Norochcholai Plant site,
Chairman of Ceylon Electricity Board E A S K Edirisinghe, said
that seventy percent of the Phase One was now complete and added
that the project will commence its test operations in the first
quarter of 2010, well ahead of its schedule.
“CEB hopes to generate power at the coal power project at a
unit cost of 7-8 rupees and anticipates passing on the price
reduction to the consumer. With Norochcholai starting commercial
operations, we can ensure that there won’t be any ad hoc tariff
hikes in the future,” he said.
Edirisinghe said that main reason for electricity to cost so
much is because of our dependence on expensive fuel oil. A
massive 55 to 60 percent of the power supply was generated by
diesel, while the share of hydroelectricity averaged between 40
and 45.
Combination of hydro and coal
Veteran
energy expert and generation planner, Dr Tilak Siyambalapitiya
believes that although the ideal energy source for Sri Lanka
should have been a combination of hydro and coal, high-cost
diesel had been promoted due to ‘commercial pressure’ with
diesel being preferred the energy source of Sri Lanka’s
Independent Power Plants (IPPs).
“Today if we had Norrochcholai Coal Power Plant up and running,
the cost of coal up to unloading point at Puttlam would be
around US $ 90 a ton which is nearly Rs 10 a kilo in today’s
prices. Since 2.5 units can be generated with this, the cost
would be only Rs 4 a unit.” Dr Siyambalapitiya said.
Rs 4 vs Rs 14
Five units can be generated by using a litre of diesel costing
Rs. 70 a litre, which means that a unit would be nearly Rs 14. A
unit generated from another new energy source promoted by CEB -
Liquefied Natural Gas (LNG) would cost Rs 10, which is still
150% more when compared with coal power. Hydropower costs Rs
five to six a unit but after 20 years the cost is just Rs 1 a
unit as the operating cost is very low.
Electricity costs in Sri Lanka were among the highest in the
world with all users paying high cost for industrial, commercial
and domestic uses and driving away the investors. Average
electricity tariff rates to industrial sector is from Rs 7.00 to
7.50 in Sri lanka; Indonesia 1.52 – 3.90; Malaysia 2.63 – 10.52;
Singapore 4.32 – 6.78; Thailand 2.89 – 7.01, according to the
Central Bank’s Annual Report of 2004.
Projected output of the power plant is 1,658 Gwh while the
installed capacity in the country was 2,544 MW (Hydro and
thermal combined) in 2006. Demand for electricity in Sri Lanka
is said to increase by about 10% annually.
Power crisis averted
It is highly commendable that the severely delayed Norochcholai
Plant is not only becoming a reality but is also in ahead of its
schedule. CEB identified coal as the most economical and
feasible power supply next to hydro, as hydro dependability is
threatened by drought and silt while thermal is an expensive
source when coal is cheaper and most widely available.
However, the average Sri Lankan had to bear brunt of ‘power
politics’ up to now, as on the one hand projects were delayed
time and again under various governments to appease from
politicians to religious leaders while on the other hand
government gave in to the cartel of fuel power plant operators
or the ‘diesel mafia’ who wanted coal power projects delayed to
accomplish their own commercial interests.
Power
politics
When the government was unable make CEB chairperson bow down to
their dictates, which were clear against interests of the
country, they appointed external ‘Power Committees’ comprised
mostly of non-energy professionals, weighing down CEB’s policy
and long-term generation plan, which had aggravated energy
crisis to what it is today.
From 1992 to 1994 the then United National Party government
appointed the infamous ‘Power Committee’ headed by then Treasury
Secretary, R. Paskeralingam, to give green light to private
power providers.
Between 1995 and 2001, under President Chandrika Bandaranaike
Kumaratunga’s regime, it was headed by the then Presidential
Secretary, K Balapatabendi. Again under the Ranil Wikremesinghe
administration from 2002 to 2004, it was re-structured as the
‘Power Supply Committee’ again headed by R. Paskeralingam.
The then Bishop of Chilaw, Rt Rev Frank Marcus Fernando along
with Catholics in the area vehemently opposed Norochcholai site
stating that the site was too close to St. Anne’s Shrine,
Talawila. The Ceylon Workers Congress (CWC) too opposed the
Upper Kotmale Project citing eviction and relocation of
plantation workers.
Private power plants along with errant CEB officials and
ignorant and corrupt politicians continued to play this power
game until President Mahinda Rajapaksa gave strict orders of
proceeding with Norochcholai and Upper Kotmale Power Projects.
As such the construction of Norochcholai Coal Power Plant was
inaugurated by President Rajapaksa on May 11, 2006, even less
than one year of coming into power.
Hydro dependence non-pragmatic
Sri Lanka is placed in a precarious situation due its high
dependence on hydro as well as expensive fuel power. In May, the
government appealed that power reduction programmes be
implemented at residential, industrial, commercial and public
sectors cutting down consumption by 30 percent in order to avert
power cuts and cautioned consumers to use electricity sparingly.
Rainfall has shown a steady decline through out 2009 and hydro
storage by end February 2009 was 3.5 GWh, down from 7 GWh for
the same period in 2008, with being just 1.5 GWh away from
reaching the 2 GWh, considered the ‘critical level’ in
hydropower generation.
CEB said that 2008/09 also recorded the lowest inflow
(rainfall) to hydro reservoirs during the period from October to
February for the last five years. Inflow was just over 1,000 GWh
down from 1,600 GWh in 2007/08 and less than half of the inflow
recorded in 2006/07, which was 2,250 GWh.
Presently daily electricity requirement of the country stood at
1.9 GW out of which one third was contributed by hydropower
projects and the rest by thermal power plants.
Power demand growing
Although Sri Lanka too saw negative growth of 6.2 percent in the
first quarter of 2009 following the drop seen worldwide caused
by the global meltdown, Sri Lanka has been indicating an average
growth of 6.5 per cent during the last 30 years according to Dr
Thilak Siyambalapitiya.
“An analysis of Sri Lanka’s compound growth of power demand
for the last 30 years shows an average of 6.5 percent per annum
although some years have even recorded a high of 14 percent,” he
said.
“In January and February 2009, the growth in demand for
electricity was a negative 6.2 percent when compared with the
same period last year. Although in 2007 the annual growth in
demand was 5 percent, in 2008 it had gone down to a mere 1.7
percent!”
However, Sri Lanka’s average consumption is 400 kilo Watt hours
per person per annum and for the country to elevate itself to
that of a middle-income level country like Malaysia, power
consumption should be around 2,000 kWh per capita per annum. The
drop is said to be short-lived and with the government
anticipating 100 percent electrification of the North in two
three or years time, the demand is set to be on the rise soon.
Although when the Northern circuit went down with escalating
hostilities, its capacity was a mere 50 MW, it will have to
catch up with accelerated development anticipated for the
region.
The Eastern Province too has already progressed in the
electrification process. However, Sri Lanka’s long-term average
growth would be around 7 percent as there will no reduction of
demand in the long run.
Sad reality
Dr Siyambalapitiya opines that although today Sri Lanka unlike
other countries in the South Asian region does not face power
cuts, the cost of generating electricity using expensive fuel to
the economy is massive.
“We have 700 MW generated from high cost diesel but if we had
encouraged the private power providers to jointly build a coal
power plant for the same amount we could have generated
electricity at just one third the cost. Sad reality is that even
now it is not happening and in any tender where technology is
not specified by CEB, the bidder will go for diesel as though
the operational cost is high, the capital cost which the firm
has to bear in a diesel plant is low,” he added.
High tariffs vs blackouts
Island’s power sector has seen long-term economical power
projects such as Norochcholai and Upper Kotmale delayed due to
political meddling. If not Sri Lanka could have become a country
with lowest tariffs in the world.
So as far Sri Lanka attempts to expand with high-cost diesel or
LNG plants Sri Lankan consumers will not be able to consume
cheap electricity. LNG although not so expensive as diesel,
would still be expensive for Sri Lanka in the long-term, whilst
combination of coal and hydro would be best suitable for the
country.
Sri Lanka at present has 9 thermal power projects along with
80 mini-hydro-plants altogether contributing nearly 700 MW to
the grid. However, the cost to import fossil fuels as well its
effect on Sri Lanka’s dwindling reserves has been enormous.
Although Sri Lanka was faced with an imminent power shortage,
over 15 percent of the output goes wasted due to system loss
while another 20 percent is wasted due to bad usage
practices.Two plants a week
Although Sri Lanka was faced with many a teething problems in
building just one coal power plant in Norochcholai, whilst China
which has the biggest hunger for energy in Asia, is building
coal plants at a rate of two projects a week.
Emerging Asian super power - India under its ambitious ‘Power
for All’ requires adding up of nearly 100,000 MW by 2012. And,
it seems, that India has made steps in this regard with two new
successful bids for Ultra Mega Power Projects (UMPPs) in Sasan
and Mundra and in January 2006, gave green light to set up nine
coal-based UMPPs of 4,000MW each.
Vietnam too is constructing a 2,000 MW in Mong Duong with
funding from Asian Development Bank (ADB), while over 50 percent
of power in the world’s largest electricity generating nation –
the USA is done using coal.
**** |